Constructing a first-class hospital for Jersey

Project Timeline

Key dates and activities for the Our Hospital Project

  • Site Selection
  • Pre-construction works initiated (surveys)
  • Preferred access route selected
  • Hospital concept design completion (RIBA 2)
  • Planning submission: Reprovision of Overdale Health Services to former Les Quennevais school site
  • Hospital and road design completion (RIBA 3A)
  • Planning submission: Demolition of disused Overdale Hospital buildings
  • Application submission: Hospital and Road
  • Planning decision: Reprovision of Overdale Health Services to former Les Quennevais School site
  • Construction works at Les Quennevais commences
  • Public Inquiry: Hospital and Road
  • Planning decision: Hospital and Road
  • Former Les Quennevais School works commence
  • Design: RIBA Stage 3 complete
  • Former Les Quennevais School works completed

PLANNING APPLICATION OVERVIEW 

1. Reprovision of Overdale health services to former Les Quennevais School site 

This application was submitted on 3 August 2021 and approved on 9 December 2021. Read more here.

2. Demolition of Overdale Hospital buildings (autumn 2021)

This application was submitted on 21 September 2021, refused on 10 March 2022 and appealed on 7 April 2022. Read more here.

3. Main Hospital 

This application was submitted on 15 November 2021 and approved on 17 May 2022. Read more here.


ARCHIVE | Community Consultation Hub

Following a rigorous public engagement and consultation programme throughout 2021, the Community Consultation Hub has now been archived and can be found via this link.